Frequent questions
We believe communication is one of the key components in providing you with a quality irrigation system. Thus, it is our intent, that by providing you with the following information, we can answer any questions that you, your board members, or patrons may have prior to starting your project.
If you have any other questions, please contact us.
What is the scope of work for a typical installation?
- Pump stations and wet wells can actually be installed at the beginning or end of the project
- Mobilization of containers, equipment, and materials
- Mainline installation
- Lateral installation


Winter Installation


Spring Installation
What do I need to know regarding wet wells and intake structures?
The type of wet well and intake structures vary depending on site conditions.- Can the pond or lake be de-watered?
- Is there a silt problem?
- Building considerations?
How much shop area does a contractor need?
- Office trailer
- 3 - 4 large storage containers
- Roll-off dumpster
- Area for equipment (tractors, trenchers, wagons, etc.)
Where is the pipe staged?
Pipe is stock-piled in shop area and strategically placed around the course-out of play areas.

Stock-piled pipe


Pipe Staging
Can our patrons continue to golf during mainline installation?
During mainline installation, patrons may continue to play with little or no disruption to their game.

Mainline Installation
Can our patrons continue to golf during lateral installation?
During lateral installation, golfers are rerouted to another hole.

Lateral Installation